Microsoft Project has a number of columns that are hidden by default in new projects. It is also possible to hide columns when working in any given project for convenience of viewing. The process used to unhide columns in Project takes a few steps but reveals a wealth of additional tools that can be used to expand the program's functionality.
Step 1

"Click" the column header to the right of the position in which the new column should appear, as in Image 1. This action will select and darken the entire column.
Step 2

"Click" the "Insert" option from the menu bar, as displayed in Image 2. This will cause a drop-down menu to appear.
Step 3

Click "Column" from the drop-down menu. This will bring up a dialogue box entitled "Column Definition," as in Image 3. This feature allows you to select the column to be displayed.
Writer Bio
James Ballou began writing professionally in 1994 for Discover Card and earned the company's highest award—The Pinnacle of Excellence in 1997. Ballou works primarily as a technical writer for corporations and has been published at BrightHub.com. He holds a bachelor's degree in business administration and a master's degree in organizational management. He is an adjunct professor of technical writing for a private university.